Monday, July 14, 2014
Paging Mr. Hadrian...
As wall building goes, we're not professionals. But we do okay.
After stacking all the various sizes and shapes of blocks in neat piles, we set about actually laying the foundation. One entire course of stones will get buried, and these have to be absolutely flat and level, because anything we stack on top of them ain't moving. So we exercised our best high school geometry to draw out the lines and curves we wanted.
As I mentioned earlier, most of the digging is way underground. Not just because the bottom course of blocks gets buried, but because our ground level is already too high and we want to lower it by a good foot or two. That means digging deep trenches before even the first blocks can go in. I was waist-deep most of the time, and tossing soil onto piles that were over my head. Thankfully, it's been warm and sunny all this week, because otherwise we might have been comfortable.
Once we got down to about the level we wanted, it was a matter of carefully putting some of the soil back in to level it. Every block has to be level front-to-back and side-to-side, but it also has to be at the right height and the exact same height as all its neighbors. Basically, the first block you set determines he position of all the others.
We'd dig out a bit, lay a few foundation stones, tweak them until they're straight and level, and then take a break. Then more digging, more levelling, more stones. We got the bottom course done in about three days.
The hardest part was laying the two curves because, well, they're not straight. But the stones are. To do an "outside" (convex) curve, you cut away part of the back of each stone to make it a trapezoid. That way, the fronts all fit together snugly while the backs are smaller than the fronts. Cue the angle grinder and diamond-tipped saw. Doing "inside" (concave) curves is easy in comparison. You just angle the blocks with their faces touching.
Once you've got the foundation course laid, building up the actual wall is relatively easy and kind of fun. You can place the differently sized blocks any way you like, but there are also suggested patterns that give a random look without funny-looking repeats or ugly gaps.
As of today, we're maybe three-quarters of the way done. The entire foundation course is laid, and about half of the wall. We've actually run out of blocks; we'll need to order a few dozen more. I can't wait to haul them in from the street.
The Stones Come to Pacific Grove
Please allow me to introduce myself. I'm a man who delivers rocks.
Our nifty little retaining wall will be made up of cast "stone" blocks that interlock together like really big LEGO bricks. You can find these in all different types, colors, and sizes, and we eventually settled on the style we liked. They had to be special-ordered (who would keep these in stock?), but that only took about a week.
Kathy and I made bets on how much the blocks would cost. My guess was lower; hers was higher. We were both wrong. It actually cost less than half of my low estimate. Bonus!
On the other hand, we were way off on the weight, and this proved to be punishing. They'll deliver the rock to the curb, but not onto the property. That's your responsibility.
I have to hand it to the driver/forklift operator, though. That guy is an artist with heavy equipment. He parked his huge truck in the middle of our street, casually blocking all the traffic, then unloaded his forklift off the back and proceeded to whirl it around like he was a circus performer on a unicycle. The entire load of blocks was on the ground in under five minutes, including lining them up nice and neat on the sidewalk. He could probably rearrange eggs in a carton with that thing.
Once he was gone we really missed him, because now we had to get all those same blocks into the backyard by ourselves. And quickly, too, since they were blocking the driveway. And it's uphill...
The invoice told us we'd just taken delivery of 7284 pounds of blocks. That's 3.5 freakin' tons! The largest and heaviest blocks weigh 75 pounds apiece; even the smallest ones come in at 18 lbs. Kathy would load three or four of these into the wheelbarrow and push them up the ramp to the backyard. I'd take a pair of the big ones on a hand truck. Over and over, rinse, repeat. If we'd been smart, we would've hired a couple of guys from the Home Depot parking lot.
By the time we finished we'd dead-lifted a total of 7 tons because, of course, you have to lift each stone at least twice: once to get it off the pallet and onto the wheelbarrow, and again out of the wheelbarrow onto the ground. That doesn't even count the work involved in humping it all up the ramp to the backyard. We figured we'd earned ourselves a greasy burger from the joint down the street.
If you need us, we'll be in the Home Depot parking lot.
Digging Dinosaurs
Poor little... whatever type of dinosaur this is. He's put up with a lot, including losing his companion to alien abduction. Now he's up to his neck in displaced dirt. That's one of the few places we could pile it without getting in our own way. We left his head out, though. There's only so much indignity a plaster dinosaur can tolerate.
Trench Warfare II
New project: Let's build a stone retaining wall in the backyard! How hard can it be?
In terms of engineering, it's pretty straightforward. But the labor involved? That's another matter.
We decided that the best way to deal with our sloping backyard was to terrace it. The neighbor's soil is at least a foot higher than ours, putting pressure on the fence. And the whole yard slopes, making it hard to walk on or enjoy. So we decided to push some of the dirt back toward the fence, and pull some of it forward. The result, we hope, will be two more-or-less flat areas with a retaining wall between them.
We started by laying out the now-familiar pile of bricks where we wanted the wall to go. You can see them here. The idea is to run part of the new wall straight, then transition into a semicircular curved section on the left side. That way we get a bit more "high" area to stash the excess dirt.
Then we used some boards to mark out the straight portions and to hold back the dirt once we started digging. And there's going to be a lot of digging.
We figure the retaining wall only needs to be about 2 feet high, but that's just the part you can see. We also need to bury part of the wall, for strength, making the whole thing about 32 inches from top to bottom.
Best of all, most of that 32 inches is going to be underground. The whole idea is to lower our average ground level, so we're going to have to dig out... well, pretty much the entire backyard. Question: Where do you put a backyard's-worth of dirt when you're digging up the backyard? Where does it all go?
In big stinkin' piles, that's where. We had to get clever about piling the dirt someplace where we wouldn't have to immediately turn around and move it again. (This strategy was not 100% successful.) The short-term plan was to shovel dirt from the high parts and throw it into the low parts, knowing full well that we'd have to shovel it back in a few days. but where else can it go? We don't have that much room to work with.
It's a bit like one of those puzzles with 15 tiles that you move around, trying to get them all in order. Except the tiles are big mounds of dirt, and it's hot outside.
Eventually, we did manage to dig a straight(-ish) trench to start the wall. We took the opportunity to bury sprinkler pipe, too, although that was almost more trouble than it was worth. Laying the pipe and putting in risers means keeping certain areas clear (no dirt piles) and it creates trip hazards all over the yard. Just adds to the excitement.
Thursday, June 19, 2014
Game of Thorns
It's springtime, so Kathy and I have started hitting the garden centers.
We started with the sprinkler system... a year ago. Our old drip sprinklers leaked, and we got hit with big water bills every time we turned it on. So we ripped out that old system and dug trenches to install new 3/4-inch PVC sprinkler pipe. Like most projects, we made some progress, stopped for a while, made some more progress, etc.
So far, three sides of the house have new sprinklers. We just need to finish the backyard. That's enough irrigation that we felt safe planting new plants. So, out with the old, in with the new.
We planted purple campanula along the front, hoping that it will drape itself over the front retaining wall. They're kind of small and straggly now, but they should spread out and cover the front planting area before long.
Next to the house we put in a half-dozen gardenias, artfully surrounded by bark dust. Next to them there's one lone begonia, mostly just because I liked it.
Along the side we put in two small hydrangeas and two privets. Our hope is that they'll all grow big and tall and create a barrier between our yard and our neighbor's. Guests staying next door at the B&B have a bad habit of stepping across into our yard, apparently believing we're part of the inn (or because they just don't care). A flower barrier should fix that problem without erecting a big fence.
Finally, we planted two pink jasmine vines on the trellis over our newly built gate. Within a year or so they should grow to cover the entire trellis. We'd thought about climbing roses there, but thorns on a gateway seemed like a bad idea.
It took a good three days before the deer came and ate our flowers. One of the hydrangeas was decapitated, and the orange begonia is missing a lot of its flowers, too. At the same time we bought the flowers we also got a big ol' jug of deer repellant, but of course, we haven't spread it around yet. Good thing we didn't buy bigger plants.
Monday, May 5, 2014
All In All, You're Just Another...
If you've been following our progress at all, you know that Kathy and I love to move bricks back and forth. It's what we do. There's nothing like spending a sunny Sunday afternoon picking up a pair of bricks and moving them 20 feet, before going back for another pair, over and over. We can while away many a happy hour transporting bricks, and often have.
After a few years(!) of this we decided we'd had enough of rearranging piles of bricks and decided to finally build (technically, rebuild) a brick patio out of them. Here it is.
We didn't do it the professional way, of course, but instead worked on it piecemeal as we found time. Once we were certain that all the major plumbing underneath the backyard was solid and reliable, we could start to smooth out the soil and get it level. We eyeballed the dimensions we wanted and made a rough count of the bricks (no problem there). Then we started at one corner, leveling the soil, planting a few bricks, checking with a level, and moving on.
After a few weeks of this we had ourselves a brick patio. The bricks are all dry-set; there's nothing holding them in place except gravity. So we mixed up small batches of concrete and cemented just the outside row of bricks to create a kind of hard ring around the patio that holds everything together.
We're on a bit of a hill, so the backyard slopes a little. That meant we had to design-in some steps, or else slope all the walkways. We chose to put a step into the front (downhill side) of the patio, and we'll probably put a few more steps along the pathways, when we get around to it.
When all the bricks were done and the outside edge was cemented in, we poured polymeric sand into all the gaps. That's special sand mixed with water-activated epoxy. Once you work it into all the cracks, you lightly mist it with water and the sand sets up hard. That should prevent weeds from growing up between all the bricks, and it helps hold the bricks in place. It's not as tough as concrete, but it's more than enough to keep the bricks from shifting around. It's great stuff, but you only have a few minutes to get the water just right. Too little water and it's just dry sand. Too much water and you'll wash away the epoxy and get... dry sand. We went through six 40-lb. buckets of the stuff, so there's exactly 240 pounds of sand in the patio now. And a whole lot of bricks.
Details, Details...
Not every project requires five trips to the hardware store. Most, but not all...
A few weeks ago we finally got around to finishing off a little trim detail we'd been meaning to get to since, oh, about 2011. This post is near the second-floor landing and has some nice scroll work on it, especially near the top. The lower portion, however, is decorated with painted plaster, which was pretty common back in ye olden tymes. The downside is that plaster collects nicks and dings and isn't as durable as wood. The bottom few inches, in particular, had gotten pretty beat up by decades of vacuum cleaners.